Rocky Reach Hydroelectric Relicensing
SERVICES: Land Surveying | LOCATION: Douglas County | CLIENT SECTORS: Dams & PUDs
We supported the Douglas County PUD in their hydroelectric project relicensing effort.
Work included:
- Establishment of 2nd order project horizontal and vertical control at approximate half-mile intervals along the left and right bank of the 50-mile reach of the Columbia River located between Rocky Reach and Wells Dams.
- Establishing additional control and placing aerial targets in support of high resolution aerial photography covering the project reservoir.
- Recovering and establishing/reestablishing and stake the boundary for the entire project
The survey required recovery of cadastral and project monumentation, analysis, and determination of cadastral and project lines along the entire reach. A 17-sheet Exhibit G project boundary map set meeting FERC requirements was prepared and provided to the District as our final deliverable.